How much time do I have once the permit is issued?

Once a permit has been issued, a permit will expire and become null and void if work is not started and an inspection is requested and has passed within 180 days from the issuance date. After the work has commenced, the permit will expire when work is suspended or abandoned for a period of 180 days. A permit will become non-renewable after an additional 60 days has passed from the expiration date.

Lack of a passed inspection within this time will serve as validation that the job has been suspended or abandoned.